Sharepart step-up transformer installed at Wilhelmshaven Power Plant

Request for Spare received on 15th of January from our German colleagues to help them out for the unforeseen outage on their step-up transformer. Delivery on site and Transfer of Title happened the 5th of February.

Last Friday, 22th of March, the 400kV transformer has been energized. During the week-end it ran under no load and starting from today the Power Plant its auxiliaries will be connected.

Due to the firm collaboration of the local technical team (S. Blind), Laborelec (M. Heylen), MP&C/MCC teams (Ch. Bouwmeester, M. Laire) and Sharepart - GDF SUEZ succeeded in installing the spare transformer of 400 ton in less than 60 calendar days.